Runway & Taxiway closures

May 2, 2022 @ 8:00 am - June 17, 2022 @ 5:00 pm

Middleton Municipal Airport (C29)

Lighting Project Schedule as of 4/26/2022

 

Phase 1

5/2/2022 to 5/20/2022

Runway 10-28, Taxiway A1, Taxiway A2, Closed 5/2/2022 7:00 AM  to 5/6/2022 6:00 PM

Runway 10-28, Taxiway A1, Taxiway A2, Closed 5/9/2022 7:00 AM  to 5/13/2022 6:00 PM

Runway 10-28, Taxiway A1, Taxiway A2, Closed 5/16/2022 7:00 AM  to 5/20/2022 6:00 PM

Runway 01/19 Closed for approximately 2 days between 5/4/2022 and 5/11/2022 Exact date TBD

 

Phase 2

5/23/2022 to 6/1/2022

Taxiway A, Closed west of Delta Lane to Runway 10 Hold Short Line

Taxiway A1, Closed

No access to Taxiway A, from Alpha Lane, Bravo Lane, Charlie Lane, including the weekend

 

Phase 3

6/2/2022 to 6/10/2022

Taxiway A, Closed East of Charlie Lane to Taxiway A2

No access to Taxiway A, form Delta Lane, and Echo Lane

Ramp and Fuel Farm access to Taxiway A, east of Taxiway A2, only

 

Phase 4

6/13/2022 to 6/17/2022

Runway 1-19 Closed

Taxiway A, Closed East of Taxiway A2, to Runway 28 Hold Short Line

Taxiway A2, Closed

No access to Taxiway A, from East Hangers/East Ramp

Ramp and Fuel Farm access to Taxiway A, west of Taxiway A2, only

 

General Notes

Active construction site, be aware of changing conditions.

 

Back taxi operations will be required during Phase 2,3, and 4 be patient and alert.

 

Dates are based on the construction schedule as of 4/26/2022, weather and other factors can and likely will change some dates.

 

Check NOTAMS during entire duration of the project

 

Contact Morey Airplane Co 608-836-1711 with any questions