Runway & Taxiway closures
May 2, 2022 @ 8:00 am - June 17, 2022 @ 5:00 pm
Middleton Municipal Airport (C29)
Lighting Project Schedule as of 4/26/2022
Phase 1
5/2/2022 to 5/20/2022
Runway 10-28, Taxiway A1, Taxiway A2, Closed 5/2/2022 7:00 AM to 5/6/2022 6:00 PM
Runway 10-28, Taxiway A1, Taxiway A2, Closed 5/9/2022 7:00 AM to 5/13/2022 6:00 PM
Runway 10-28, Taxiway A1, Taxiway A2, Closed 5/16/2022 7:00 AM to 5/20/2022 6:00 PM
Runway 01/19 Closed for approximately 2 days between 5/4/2022 and 5/11/2022 Exact date TBD
Phase 2
5/23/2022 to 6/1/2022
Taxiway A, Closed west of Delta Lane to Runway 10 Hold Short Line
Taxiway A1, Closed
No access to Taxiway A, from Alpha Lane, Bravo Lane, Charlie Lane, including the weekend
Phase 3
6/2/2022 to 6/10/2022
Taxiway A, Closed East of Charlie Lane to Taxiway A2
No access to Taxiway A, form Delta Lane, and Echo Lane
Ramp and Fuel Farm access to Taxiway A, east of Taxiway A2, only
Phase 4
6/13/2022 to 6/17/2022
Runway 1-19 Closed
Taxiway A, Closed East of Taxiway A2, to Runway 28 Hold Short Line
Taxiway A2, Closed
No access to Taxiway A, from East Hangers/East Ramp
Ramp and Fuel Farm access to Taxiway A, west of Taxiway A2, only
General Notes
Active construction site, be aware of changing conditions.
Back taxi operations will be required during Phase 2,3, and 4 be patient and alert.
Dates are based on the construction schedule as of 4/26/2022, weather and other factors can and likely will change some dates.
Check NOTAMS during entire duration of the project
Contact Morey Airplane Co 608-836-1711 with any questions